     8.0 MONITORING MECHANISM AND APPLICABILITY

  8.1

STATE LEVEL MONITORING COMMITTEE:

12“The GOAP, Department of Revenue, Shall constitute a State Level Monitoring Committee, to be chaired by the Principle Secretary/ Secretary, Department of Revenue for reviewing and monitoring the progress of implementation of resettlement and rehabilitation scheme/ plan relating to all projects to which this policy applies. The committee shall meet at lest once in three months to review and monitor the implementation of R&R plan in all projects. The committee will have the following or his nominee not below the rank of Joint Secretary as its Members:

  1. Special C.S. & CCLA, Chairman

  2. Commissioner for R&R & E.O.Secretary to Govt.

  3. Prl. Secretary, Revenue

  4. Secretary, Planning

  5. Secretary, Social Welfare

  6. Secretary, Tribal Welfare

  7. Secretary, MA & UD

  8. Secretary, PR & RD

  9. Secretary, Housing

  10. Secretary, Education

  11. Secretary, Agriculture

  12. Secretary, Women and Child Welfare

  13. Secretary, Energy

  14. Secretary, Law

  15. Secretary, Finance

  16. State Level N.G.O

  17. Chief Engineer/ Project Administrator Special invitee

  18. Secretary, Requisition Department”12


  8.2

THIRD PARTY CONCURRENT AUDIT OF IMPLEMNTATION:

Chairman State level committee shall put in place mechanism for each project for third party concurrent audit of implementation of R&R plan. The audit report of such concurrent audit shall be placed before state level committee form time to time.

  8.3

PROJECT LEVEL MONITORING COMMITTEE:

The Administrative Department of the project for which land is being acquired, shall constitute a Project Level Monitoring Committee, to be chaired by the District Collector of the district in whose jurisdiction the main component of the project lies, in case main component projects spreads over more than one district, senior most of the District Collectors shall chair the committee for reviewing and monitoring the progress of implementation of resettlement and rehabilitation scheme/ plan relating to the project to which this Policy applies. The committee shall meet at least once in two months to review and monitor the implementation of R&R plan

The Committee will have following as its members”

13 “Joint Collector/ P.O ITDA- Convener

R&R officer- RDO/ Sub Collector of the division

SDC/ RDO/ Sub Collector, Land Acquisition

Project Director, DRDA

Chief Executive Officer, Zilla Parishad

District Panchayat Officer

District Education Officer

District Medical and Health Officer

District Level representative of DISCOM

Superintendent Engineer, RWS PanchayatRaj Department

Three members from PAPs, one at least women

One member from local NGO

Superintendent Engineer, Project site

Superintendent Engineer, Panchayat Raj

Superintendent Engineer, R&B

Executive Engineer, Social Welfare Department.”13

    APPLICABILITY OF POLICY:

  8.4

THE POLICY ON THE RESETTLEMENT AND REHABILITATION OF PROJECT AFFECTED FAMILIES AND PROJECT DISPLACED FAMILIES (PRR-2005) SHALL COME INTO EFFECT FROM THE DATE OF ISSUE OF GOVERNEMNT ORDER.

  8.5

The Project to which this policy is made applicable, the provisions of G.O. Ms 98 Irrigation (Project Wing) Department Dated:15.4.1986 and G.O.Ms.No.64 Social Welfare (T) Department, Dated: 18-4-1990 or any other order issued by any other department on this subject shall cease to operate form the date of commencement of this policy.

 
  12.

. Substituted for para 8.1 vide G.O.Ms.No.184, I & CAD (PW:LA-IV- R&R) Dept, DT: 09-09-2008.

  13.

Added vide G.O.Ms.No.101, I & CAD (PW: LA-IV- R&R) Dept, DT: 24-08-2009.

     